The first of six homes for stage 1 of the village has commenced. Each home will take about six months to complete.
The asphalt road in the Village has been completed, and the first dwelling has been framed and roofed. The second dwelling slab is planned to be poured in the week commencing 3-7-23 (weather permitting).
Marketing the village is well underway and anyone interested in learning more is invited to take a look at plans and concepts for the interior and exterior finishes. Visit the website at www.edwardrivervillage.com